A painter on a step-ladder repainting an empty school corridor during summer in Ottawa

A school’s facilities manager called me in June to book an August repaint — by then most of the summer painting window was already gone

A facilities manager called me one June about repainting a school wing — eight classrooms and a main corridor — before staff came back in late August. Reasonable ask. The problem was the calendar: the usable summer window is shorter than almost everyone plans for, and the crews who do this work well fill it months ahead. This post is for the people who book summer painting — school and college facilities leads, property managers, and condo boards in Ottawa — on how to lock a realistic summer 2026 schedule before the window closes.

A painter on a step-ladder repainting an empty school corridor during summer in Ottawa

1. The summer window is shorter than the calendar says

Everyone sees July and August and counts eight weeks. In practice you rarely get them. A school hands over the building once exams, deep cleaning and floor work are done — often not until the second week of July — and needs it back, fully cured and furniture replaced, before staff return in late August. That can leave six usable weeks, not eight.

Paint also needs time the calendar doesn’t show. A coat has to cure before furniture goes back against a wall, and in a humid Ottawa July that can mean close to a full day between coats instead of a few hours. Pack a full repaint into a window that’s quietly two weeks shorter than you assumed, and something gives — either the scope shrinks or the prep does, and skipped prep is where paint failures start.

Condos have the same squeeze in a different shape. The low-disruption stretches — when the AGM isn’t looming, when balconies are dry, when fewer residents are home — are narrow too, and every board on a manager’s roster wants the same weeks. I wrote about keeping that kind of work tolerable for residents in my note on painting an occupied condo building.

What to look at: your real handover and hand-back dates, not the school-calendar dates. Count the working days between “we get the keys” and “everything must be back in place,” then subtract weather and cure days. That number is your actual window.

2. Everyone wants the same eight weeks

There’s a fixed amount of qualified institutional painting capacity in Ottawa, and in July and August every school board, college, condo and office wants it at once. Booking in spring versus booking in July is the difference between a dedicated crew that planned your job into its season and a crew scrambled together from whoever’s free — or a start date that slides into September, which for a school means working around students.

This isn’t a scare tactic about availability; it’s just how trade calendars work. The contractors who handle institutional work well are quoting summer jobs in March and April and committing crews by May. By late June, the good ones are spoken for.

An empty classroom mid-repaint with masked baseboards, drop cloths and a step-ladder during summer

What to look at: ask any contractor you’re considering, point-blank, what their July and August calendar looks like and who specifically would run your job. “We’ll fit you in” in June is a very different answer than a named crew and a committed start date.

3. The decisions that have to happen before you can book

You can’t lock a crew on “we want it painted.” A bookable scope needs colours chosen, surfaces assessed, and access sorted — and in institutional buildings that middle part bites. Many of Ottawa’s schools and older institutional buildings predate the 1990s, which raises two questions that have to be answered before a brush touches a wall: is there lead in the old paint, and is there asbestos in the textured ceilings or other materials. If either is present, the work needs proper handling and added steps — not something you want to discover in week one of a six-week window.

Then there are approvals. Board sign-offs, reserve-fund or capital-budget confirmation, colour choices that go to a committee — those take weeks on their own. Started in spring, they’re done before booking. Started in June, they eat the window.

What to look at: pull the paint records or building-material reports for any pre-1990 building now. If there’s any doubt about lead or asbestos, get it tested in spring — not after the crew is standing in the hallway.

4. How to lock a summer schedule that holds

A summer plan that survives contact with reality has a few things in it. A hard end date everyone designs backward from — first day of class, move-in day, the AGM. A phased sequence, so the building comes back in usable pieces if weather or a surprise eats a few days. Buffer days for Ottawa’s humidity and the odd heat wave that stretches cure times. And it’s in writing now, with the crew named and the start date committed — not a verbal “should be fine.”

The jobs that go sideways are almost never the over-planned ones. They’re the ones booked late, scoped loosely, and started hoping the weather and the calendar would cooperate.

What to look at: whether your summer painting is on paper today — dates, scope, crew, contingency — or still living as an intention. If it’s an intention in June, it’s already late for August.

What to do if you’re booking summer work

If you’ve got a school, college, condo or institutional building that needs paint before the fall, the move now is to scope and book it — not to wait for a quiet week that isn’t coming. I do institutional and condo painting assessments and plan summer schedules across Ottawa, including Kanata, Nepean, Barrhaven, Orléans, Stittsville and Manotick: 613.325.3011 or yasir@heims.ca, and our full commercial and institutional scope is on the services page.

— Yasir, HEIMS Construction

HEIMS Construction is an Ottawa commercial and residential painting contractor serving condominiums, multi-residential buildings, institutions and commercial properties across Ottawa and Eastern Ontario. Members of BOMA Ottawa, the Ottawa Construction Association, CCI Eastern Ontario and ContractorCheck.